top of page
Search
  • Calum McCulloch

Eldon House

November 2023 – Eldon House, London – CAT A refurbishment, Project update.

Project is progressing, and well into its 7th month on site, and starting to take shape on the floors waiting for the next stage of fitout.


The project is for the comprehensive refurbishment of all floors of the building internally and externally also.

 

Internally:  Structural Alterations to create an improved flow of space, New WC Fitout at each floor level, Ceilings, Raised Floors, Drylining, Exposed Brickwork, Exposed Period columns and beams, Exposed services fed from new Service Risers, Reception upgrade/fitout, Staircase upgrades/fitout, mezzanine floors reworked so connect directly to main office floors, decorations and high-level finishes throughout.

 

Externally: New rooftop plant, replacement Schuco windows, Cleaning of façade brick & stonework, new glass and steel raked mansard along Wilson St at 6th floor level, all topped off with a new 7th floor pavilion glass/clad extension.

 

Started April 2023, completion September 2024.

 


Client: Cli-Dartriver (CLID)

Project Manager: Capital & Provincial Project Management and Building Consulting Ltd

Cost Management:  Exigere

Architect: Lifschutz Davidson Sandilands

M & E Consultant: Flatt Consulting

Structural Engineer: HTS

31 views0 comments

Recent Posts

See All
bottom of page